Project Overview    
   
Kingston General Hospital
  Kidd Wing 0 (Central Processing)

Overview:

  • Complete renovation and expansion of Central Processing Services
  • Renovation/relocation of Materiel Management & Respiratory Therapy services

What's Happening (Highlights only):

  • Phase 1 Begin construction of new purchasing department, mail room, print shop and respiratory therapy area in FAPC 0
  • Phase 2 Move departments into new space on FAPC 0 and begin construction of bulk stores, mail room, clean linen and dispatch areas
  • Phase 3 Move departments into areas completed in previous phase and begin construction of decontamination and sterile area of Central Processing Services
  • Phase 4 Move decontamination, sterile area, offices, locker room and clean linen to new space and construct cart holding, office and materiel management cart building area
  • Phase 5 Move temporary stores to final location, build offices and cart holding area

Benefits:

  • Additional capacity to support access to surgical services
  • Improved environment to support infection control requirements
  • Enhanced ability to recruit and retain leading health care professionals