Project Overview    
   
Kingston General Hospital
  Burr Wing 3 (In-centre Dialysis Unit)

Overview:

  • Moving from current space on Davies 2 to new floor on Burr 3
  • Expansion from 26 to 40 treatment stations to meet growing patient needs

What's Happening (Highlights only):

  • Phase 1 Structure will be constructed
  • Phase 2 New elevators will be completed
  • Phase 3 Completion of unit and relocation from Davies 2

Benefits:

  • Waiting areas will better accommodate scooters, wheelchairs, etc.
  • Improved access for patients, with Burr wing entrance made up of a two-lane circular driveway off of King Street
  • Better design to enhance privacy and preserve dignity of patients
  • Additional space to support education of health care providers
  • Enhanced ability to recruit and retain leading health care professionals
  • Significant infection control improvements